Hi Experts,
I have a query on generation of leave quota through TEV. I am using negative time evaluation and at the same time I am capturing IT2002 also. With this I executed PT60 from 1st Jan'15 to 31st Jan 2015. I have seen that quota is getting generated accurately. Consider 2002 present for entire month.
Let's say, we have CL 15 days and EL 2 days. Now I created an entry in IT2001 (CL 1 day) with effective from 14th Jan today. Now again when I am running TEV with Evaluation up to 31st Jan, I saw the recalculation started from 12th Jan whereas It should have started from 14th jan to 31st Jan, as I understood. And there is a split in IT2002 record....12th jan to 13th jan and 15th to 17th as 14th I had taken a CL.
but if I give Forced recalculation as of 1st Jan, then it is running for the entire month of Jan. I checked IT0003 and there PDC recalculation date was set to 12.01.2015. Why? Shouldn't it set to 15th Jan?
Please let me know if I am missing anything.
Thanks...