Dear Experts,
As i know that work center can be a machine or group of Machines. My client has 96 machines in Weaving department where grey fabric is being made. I have two choice:
- Open 1 work center with 96 capacities
- Open 96 work center with each capacity
If i go with 1st option, can i get individual machine reporting based on production order i.e. which machine is assigned to which production order & which machines are free and which machines are fully loaded & which machine has partially capacity available?
IF YES? please explain in detail
otherwise i have to go wi;6th 2nd option (which i don't want due to excessive amount of work centers)
Waiting for your reply