Hello Avinash,
Thanks for your prompt reply.
I maintained the Resource class as "Business Partner" instead of HR resource and with this now I'm able to see the BP under the node successfully.
But here the question is , since Resource class can contain any one entry , either Business Partner or HR resource, how can we tackle a situation, where both resources (BP and HR res) are required ?
We're using the HR employees (migrated from HCM) along with the BP (created within MRS).
Here as per business, HR resources are assigned to demand. But in a case, on a date, where no HR resource is available or Overloaded , we need to look for contract worker to share the work.
How this can be achieved with only one option mapping in Resource Class??
Please guide here..
Thanks