Hi,
Here are the steps that I followed.
(1) Created the material in the plant.
(2) Created the BOM for that material.
(3) Created the Recipe in C201. without Recipe - material assignment.
(4) Created the Prod Version using the MM02->MRP 4 view. Assigned the recipe number also.
(5) Going to C202 to do the recipe-material assignment. I enter the recipe and group counter number. Click on the "Material List" in menu. In the pop up I select "Other Material" option, then I enter material, plant and the prod version number that I created in STEP 4. I get the below error:
error message: "Select a valid production version for the recipe".
I think the SAP is not expecting the Prod Version to be entered here. See if i only enter material, plant and press enter , it automatically pick the prod version that was created in MM02 -> Mrp 4 view. If there are > 1 pro version for that material, plant, after hitting the enter key it shows the list of the prod version in the next pop up screen. From that we have to select any one.
But for some reason, if i enter the prod version in the previous pop up along with material, plant. it gives this error, instead of going to next screen of the recipe - material assignment.
Thanks!
Puneet.
FULL error message details:
Select a valid production version for the recipe
Message No. C5606
Diagnosis
The production version is assigned to another master recipe. Select a production version for the current recipe.
Procedure
If no production version exists for the current recipe, the system leads you to create a production version using the function "material list". You can also maintain a production version for the current recipe using the "material recipe assignment" function.